At the daily standup we found that one card that was estimated for an hour or so took two days' work of a pair!. Well shit happens but thing had to be done, so we've shed a tear and moved on. Anyway our velocity isn't gonna be what I expected, too bad. As the last weeks velocity dropped from 15 to 9, I hove to stay at least at this level. This places us having 6 more one-week iterations to come, and the magical date is in 3 weeks. I can't do anything about it. Or can I? What I did was communicated that to the executives and managers loud and clear, I have no idea what they're going to do about it. I hope they're not blind.
I have to speed up my actions and publish the projected project path every Monday, not Wednesday or Thursday. It's 2-3 days lost!